Lausanne: interlocking system construction site.

The safety and traffic management installations (interlocking systems) in Lausanne have reached the end of their lives. 

The project covers the area from the "pont du Languedoc" bridge in the east to La Conversion and Pully.

This work needs to be done before Lausanne rail station can be extended. 

All about the project

We would like to warn you, as a resident affected by this construction work, about occasional disruptions by giving you regular updates. You can read our calendar and our news updates to find out about upcoming work.

Calendar.

  • 2016 – start of construction
  • 2016-2017 – underground construction 
  • 2018-2019 – construction of the service building and test phase
  • November 2020 – start of operations
  • 2021 – end of construction

Engineering work updates.

We are currently carrying out the following work:

The building was completed in June 2019. The work being carried out up until the end of this year will enable us to equip the building interior with all the cables and computers it needs to function as an interlocking system. This will be followed by a technical test phase. 

Where?

Treyblanc district, Lausanne

What?

Interior construction work will take place during the daytime only 

When?

June to December 2019

Further content